PM Surya Ghar Subsidy in Telangana 2026 — How to Apply Step by Step
Updated March 2026 | By Sri Ishaan Solar Team
The PM Surya Ghar Muft Bijli Yojana offers up to ₹78,000 subsidy for residential rooftop solar in Telangana. Here's exactly how to get it.
Subsidy Amount (2026 Rates)
| System Size | Subsidy Per kW | Total Subsidy |
|---|---|---|
| 1 kW | ₹30,000 | ₹30,000 |
| 2 kW | ₹30,000 | ₹60,000 |
| 3 kW | ₹30,000 + ₹18,000 | ₹78,000 |
| 4 kW+ | 20% of benchmark cost | ₹78,000 (max for residential) |
Who is Eligible?
- Indian resident with a residential electricity connection
- Must own the property (or have owner's NOC)
- Roof must have adequate space (~100 sq ft per kW)
- Single-phase connection: up to 5 kW
- Three-phase connection: up to 10 kW+
- Only one subsidy per household
Step-by-Step Application Process
Step 1: Register on PM Surya Ghar Portal
Visit pmsuryaghar.gov.in and register with:
- Your TSSPDCL/TGSPDCL consumer number (on your electricity bill)
- Aadhaar number
- Mobile number
- Bank account details (for direct subsidy transfer)
Step 2: Submit Application
- Select your state (Telangana) and DISCOM
- Choose system size (we recommend 3 kW for most homes — maximum subsidy)
- Upload electricity bill copy
- Upload roof photo
Step 3: Feasibility Approval
TSSPDCL/TGSPDCL reviews your application and issues feasibility approval (usually 7-15 days).
Step 4: Choose an Empanelled Vendor
Select a registered vendor from the portal list. Sri Ishaan Solar is an empanelled installer — we handle all paperwork for you.
Step 5: Installation + Net Meter
Your vendor installs the solar system and applies for net metering. DISCOM installs the bi-directional meter (usually within 15-30 days after installation).
Step 6: Commissioning + Subsidy
After DISCOM inspection and commissioning, subsidy is credited directly to your bank account within 30 days.
Documents Needed
- Electricity bill (latest)
- Aadhaar card
- Bank passbook or cancelled cheque
- Roof ownership proof or NOC
- Passport-size photo
Common Questions
How long does the process take?
Total timeline: 30-60 days from application to subsidy credit.
Can I get subsidy for commercial property?
No — PM Surya Ghar is residential only. Commercial properties can still install solar but without this subsidy.
What if my application is rejected?
Common rejection reasons: wrong consumer number, insufficient roof space, duplicate application. Fix the issue and re-apply.