DISCOM అప్రూవల్ ఎలా తీసుకోవాలి? — Complete Guide

How to Get DISCOM Approval for Solar in Telangana — 2026

Updated April 2026 | By Sri Ishaan Solar Team

Telangana లో solar install చేయాలంటే DISCOM (TSSPDCL/TSNPDCL) approval mandatory. Net metering, PM Surya Ghar subsidy — everything DISCOM approval based. ఈ guide లో full process, documents, timeline, common problems & solutions.

DISCOM Approval ఎందుకు అవసరం?

Step-by-Step DISCOM Approval Process

Step 1: Application Submission

Timeline: Day 1

TSSPDCL/TSNPDCL online portal లో application submit. Required information:

Note: Sri Ishaan Solar application preparation + submission handle చేస్తుంది.

Step 2: Technical Feasibility Study

Timeline: Day 1-15

DISCOM engineer checks:

Step 3: Feasibility Report & Approval

Timeline: Day 15-20

Positive report → approval letter with conditions. Negative report → reasons stated, solutions suggested.

Step 4: Installation Permission

Timeline: Day 20-25

Approval letter receive → installation begin. Approved specifications exactly follow చేయాలి.

Step 5: Installation Completion & Report

Timeline: Day 25-40

Installation complete → completion report submit with:

Step 6: DISCOM Inspection

Timeline: Day 40-50

DISCOM inspector site visit → physical verification → safety compliance → meter testing.

Step 7: Bidirectional Meter & Commissioning

Timeline: Day 50-60

Old meter replace → bidirectional meter install → final readings → commissioning certificate.

Required Documents Checklist

DocumentWho Provides
Application form (filled)Sri Ishaan Solar
Latest electricity billCustomer
Aadhaar card copyCustomer
Property ownership proofCustomer
Single line diagram (SLD)Sri Ishaan Solar
Panel specifications & certificatesSri Ishaan Solar
Inverter specifications & certificatesSri Ishaan Solar
Vendor empanelment certificateSri Ishaan Solar
Earthing test reportSri Ishaan Solar
Roof photosSri Ishaan Solar

Customer provides just 3 documents. మిగతా అన్నీ we handle.

Common Rejection Reasons & Solutions

1. Transformer Capacity Full

Problem: Local transformer already at maximum capacity — new solar connection not possible.

Solution: Request transformer upgrade (takes 2-3 months), or reduce proposed system size to fit available capacity.

2. Technical Issues — Voltage

Problem: Grid voltage at your location already high — additional solar injection will exceed limits.

Solution: Install voltage regulation equipment, or reduce system size.

3. Incomplete Documentation

Problem: Missing documents or incorrect specifications.

Solution: We prepare all technical documents — this never happens with Sri Ishaan Solar.

4. Non-Empanelled Vendor

Problem: Vendor not registered with MNRE/TSREDCO — automatic rejection.

Solution: Always use empanelled vendor. Sri Ishaan Solar is fully empanelled.

TSSPDCL vs TSNPDCL — Contact Details

DetailTSSPDCLTSNPDCL
AreaSouth TelanganaNorth Telangana
CitiesHyderabad, Rangareddy, Mahbubnagar, Nalgonda, KhammamWarangal, Karimnagar, Nizamabad, Adilabad, Medak
Helpline19121912
Websitetssouthernpower.comtsnpdcl.in

Tips for Faster Approval

  1. Application complete గా submit — no missing fields
  2. SLD technically accurate — DISCOM standards follow
  3. Empanelled vendor use — automatic credibility
  4. Follow up weekly — portal + helpline
  5. Inspector visit కి system ready గా ఉంచండి

We Handle Everything

DISCOM paperwork complicated — కానీ మీకు worry లేదు. 8+ years experience తో 500+ DISCOM approvals successfully processed.

DISCOM Approval Help — WhatsApp →

Or call: +91 78424 61888

Related Articles

← Back to Sri Ishaan Solar